Agile project management

Agile is a name for many different methods, each of these implementation is unique. The included methods are Scrum, XP, and Kanban.

The Agile manifesto

  • Individuals and interactions over processes and tools
  • Working software over comprehensive documentation
  • Customer collaboration over contract negotiation
  • Responding to change over following a plan

Agile projects

Traditional development: |Requirements->|Design->|Implementation->|Testing->| Done! Agile development: |R->|D->|I->|T->| |R->|D->|I->|T->| |R->|D->|I->|T->| Done!

Agile focuses on... * Maximizing return on investment (ROI), delivering business value. * Quickly delivering working code. * Expecting and managing changes.

Agile SPM involves gradual detailing, prioritized work order that are just-in-time, and independent teams.

Exploration

  • Define high-level requirements
  • Prioritize from business perspective
  • Explore / prototype

Planning

  • Prioritize user stories
  • Backlog (scrum)
  • Story cards, story board, Kanban board
  • Re-estimate, for each sprint
  • Select set of stories for iteration according to capacity

Kanban board

Simplest version - columns for to-do, in progress, done

Common version - Backlog, Ready, Coding, Testing, Approval, Done columns

Used to, visualize workflow, limit work-in-progress, pull work from column to column, monitor, adapt, improve etc.

Time boxing

  • Time-box fixed deadline by which something has to be delivered
  • Typically two to six week iterations
  • Develop the most prioritized stories first

Development

  • Iterations a.k.a. sprints
    • Scrum: 30 days prescribed, but varies in reality
    • XP: shorter, 2 weeks
  • Work in prio order
    • Scrum: team chooses stories in sprint planning
    • XP: team chooses stories strictly according to agreed prio
  • Managing change
    • Scrum: no changes in scope / stories during sprint
    • XP: changes allowed

Activity planning

  • Product Owner/Customer defines and prioritises User stories
  • Backlog or Story card management
  • Dependencies are built into the prioritised list, i.e. not explicitly marked

Effort estimation

  • Early estimates during exploration phase
  • User stories estimated as part of iteration/sprint planning
  • Time (man/person hours/days) or relative estimates (story points, bananas, gummy bears)
  • Planning game (XP) or Planning poker (Scrum)

Resource allocation

  • Capacity driven
    • Project level: In exploration phase
    • Iteration level: In iteration planning
  • Within iteration: team pull, i.e. self-allocation

Risk management

  • Built into the process, e.g. stand-up meetings: Hindrances?
  • Transparency, openess with information
  • Iteration demos with customer / product owner

Traditional risk management techniques can be used, but not prescribed by Agile methods as such.

Monitor and control

  • Progress monitored by asking ”How much work remains?”
  • Frequent status checks -> Burn-down charts, see monitor and control chapter.
  • Management does NOT control in agile, the ”pigs” (Product owner, scrum master, team leader) do!
  • Team is responsible for managing itself – Team pull!

Team responsible for its own work practice / process * Regular feedback loops: pair programming, daily stand-up. * Sprint retrospectives.

Scaling agile

  • Designed for small scale – 1 team
  • Scalable with Scrum-of–Scrums, shared backlog
  • Upscaling specific to each organisation
             ____
            | AX |            <-- Scrum of Scrums of Scrums
              / \____..
           __/_
          |ABCD|              <-- Scrum of Scrums
    _________|_________
 __/_   __/_   _\__   _\__
|AAAA| |BBBB| |CCCC| |DDDD|   <-- Scrum teams

Strengths

  • Feedback from early stages used in developing latter stages.
  • Shorter development thresholds
  • Quickly delivers working increments
  • User gets some benefits earlier
  • Reduces ‘gold-plating’
  • Avoids unnecessary overhead, e.g. keeping docs updated
  • Shorten comm paths within cross-functional teams

Weaknesses

  • Refactoring causes software breakages-
  • Loss of economy of scale.
  • Weak / missing documentation – especially for large scale.
    • Dependence on personal knowledge.
    • Decision rationale, reqst-tc tracing may be lost.
  • Generalists have weaker specialist competence, e.g. requirements, testing, architecture.
  • Weak long-term and overall perspective.